A 12,203-Square-Foot Retail Building at The Marketplace in Highland Village Has Its Site Plan — Again
The same lot at 2150 Village Parkway has now been approved three times. This time, the developer says it’s ready to build.

If you drive Village Parkway and have been eyeing that empty lot next to the Phase 1 building at The Marketplace at Highland Village, here is what you need to know: the site plan is approved, the owner says they are ready to move, and the city is projecting a 2027 completion.
Highland Village City Council voted 7–0 on Tuesday, Nov. 11, 2025, to approve Resolution 2025-3224 — a detailed site plan for Lot 7B at The Marketplace at 2150 Village Parkway. The building, owned by Village Partners Group, LLC, would be approximately 12,203 square feet for retail use.
This is the third time the same plan has cleared council. The site plan was originally approved in October 2017, and because development did not begin within one year of that approval, it expired. In June 2021, the owner returned requesting a drive-thru use, which required a Conditional Use Permit — council denied it. In December 2021, the applicant came back with the original plan minus the drive-thru, and council approved it. Development still did not begin within the following year, and that site plan expired as well.
The November 2025 approval carries the same footprint and design as the 2021 version — the requested site plan is exactly the same as the one council approved on December 14, 2021. A few minor additions are included: the applicant sought extra signage on the north and south elevations and an eight-foot sidewalk along Village Parkway. Before the vote, the Planning and Zoning Commission unanimously recommended the site plan forward to City Council at its October 21, 2025 meeting, 5–0.

Staff noted the building is presented as a shell, so tenant finish-outs will return for permitting separately. The approval does not tell you who will move in. That comes later, as individual tenants sign leases and pull their own permits. The city’s Community Development Projects page describes the project as constructing an approximately 12,000-square-foot retail building with finish-out planned for up to five retail establishments, with anticipated completion in 2027.
One practical thing to keep in mind: city code sets a one-year deadline — once a site plan receives final approval, the clock runs, and construction must get underway before that year is up or the site plan expires. That clock started running on Nov. 11, 2025. If ground is not broken by November 2026, Village Partners Group would need a fourth council approval before construction could begin.
The approvals are done. Permits are next.
- City of Highland Village — Council Meeting Press Release, Nov. 12, 2025
- Highland Village City Council Agenda Item 14 — Resolution 2025-3224 (Nov. 11, 2025)
- Highland Village Planning & Zoning Commission Minutes — Lot 7B Site Plan
- City of Highland Village — CivicAlerts Nov. 13, 2025
- Highland Village Community Development Projects
- City of Highland Village Zoning Ordinance — Site Plan Lapse Rules
- Highland Village Retail Spaces for Lease
- MEETING MINUTES OF THE REGULAR MEETING HIGHLAND VILLAGE CITY COUNCIL
- FAQs - CivicPlus.CMS.FAQ
- 1. Call to Order/ Roll Call.
- VIII: NONRESIDENTIAL OVERLAY ZONING DISTRICT - City of Highland Village, TX