Trotter Park Breaks Ground September 7 — $10.25M, 16 Months, and 12 Pickleball Courts

That empty lot on Cross Timbers Road is about to get very loud — here's what's going in and when it ends.

2026-08-092 MIN READ#Trotter Park · #Parks & Recreation · #Construction · #Cross Timbers Road · #Pickleball · #West Flower Mound · #Denton County
Empty grassy parcel at 4551 Cross Timbers Road where Trotter Park construction begins September 7
Photo: The Flower Mound Bee Social Team

If you drive past 4551 Cross Timbers Road, you know the spot. A flat, grassy parcel that has spent years as Flower Mound's most ambitious placeholder. That changes in less than a month.

Construction kicks off September 7, with a TDLR-registered completion date of January 7, 2028, and an estimated cost of $10,250,000. Just under 16 months of active work on the west side of town.

Trotter Park by the Numbers
$10.25MTotal project cost$750KTPWD grant12Pickleball courts
Source: TDLR project registration TABS2026024315, Town of Flower Mound

The scope is bigger than most people expected. The project calls for a new parking lot, playground, one basketball court, two tennis courts, 12 pickleball courts, and a loop trail around an open green space. The finalized master plan also includes an entry plaza, a restroom, a large open lawn, and an enhanced native area. The half-mile looped trail will circle the whole site — council asked for a combination of concrete and crushed granite or a similar product when approving the design.

The pickleball count is worth a closer look. Council bumped the planned courts from eight to 12 when it approved the master plan in July 2024. Twelve courts on one site makes this a real destination, not just a neighborhood amenity.

Twelve outdoor pickleball courts planned for the new Trotter Park in Flower Mound
Photo: K (Pexels)

Funding comes from a few sources. The town received a $750,000 Texas Parks and Wildlife outdoor recreation grant toward the project. As a condition of that grant, Flower Mound must keep Trotter Park publicly accessible, properly maintained, and designated as park land in perpetuity. The remainder of the $10.25M comes from town funds.

For neighbors along Cross Timbers Road, the practical reality is 16 months of construction traffic and noise on an active corridor. The town has not yet published a phased-closure or access schedule. Check flowermound.gov or call Parks and Recreation at 972-874-6425 for updates as work begins September 7.

Sources
  1. TDLR TABS Project Details — Trotter Park (TABS2026024315)
  2. Construction Projects | Flower Mound, TX - Official Website
  3. All Parks | Flower Mound, TX - Official Website
  4. MHS Planning & Design — Trotter Park Project Page
  5. Trotter Park design gets OK from Flower Mound council — Community Impact (July 2024)
  6. Flower Mound gets $750K state grant for Trotter Park — Community Impact (January 2025)
  7. Trotter Park Master Plan
  8. Have you been following the Trotter Park design process ...
  9. Flower Mound town officials ask for feedback on Trotter Park | Dallas - Fort Worth | Community Impact
  10. Designs for new Flower Mound park to be revealed | Community Impact
  11. Flower Mound town officials ask for feedback on Trotter Park | Community Impact
ShareXFacebookEmail
← back to the front page