Fire Station 5 on Spinks Road Wrapping Up a $2.5 Million Rebuild

The roof trusses failed, the shoring came down, and now the interior work is nearly done — Station 5 should be back to full strength by the end of November.

2026-11-232 MIN READ#Fire Department · #Fire Station 5 · #Public Safety · #Infrastructure · #Construction · #Spinks Road
Fire station exterior with apparatus bay doors open
Photo: Mehmet Suat Gunerli (Pexels)

If you live near Heritage Park or anywhere along the Spinks Road corridor, the fire station at the end of your response-time chain has been through a serious rebuild. It's nearly done.

Flower Mound Fire Station 5 at 800 Spinks Road is in the final stretch of a $2.5 million reconstruction. The town's construction projects tracker, updated Monday, Nov. 9, confirmed that contractors finished installing trusses and completing the outer roof, removed the temporary shoring that had been holding up the structure, and are now working through interior finishing. The project is anticipated to be complete in November 2026.

Here's the backstory. Engineers found that the station's roof trusses had failed, making part of the building unsafe. Staff installed shoring and struts to keep one bay operable while the town pursued an emergency contract. The approved scope covers reconstruction of the affected bay and its mechanical and electrical work, a new metal roof to extend service life, and a full bay exhaust system for firefighter safety. Council awarded the construction contract in spring 2026, and the contractor moved to work shortly after. Fast timeline for a job this involved.

A station running on reduced capacity is not the same as a fully operational one, even when crews never stopped responding. Getting Station 5 back to full capability matters for the neighborhoods it covers.

Fire truck inside station apparatus bay
Photo: James Collington (Pexels)

Worth knowing before you mark your calendar: a completed building and a fully staffed, operational station are two different things. Equipment still has to be repositioned and the facility confirmed ready for service. The town has not announced an official opening or staffing date. End of November is the construction target, and the operational piece follows from there.

Station 5 sits next to the Community Activity Center on Spinks Road, well away from the Canyon Falls and Furst Ranch growth on the west side of town. That western coverage story belongs to the separate $20 million Station 6 project, expected to open in 2027. Station 5's rebuild is a different matter: getting an existing facility back to the shape it needs to be in. The construction finish line is this month.

Sources
  1. Town Facilities – Fire Station No. 5, flowermound.gov
  2. History
  3. Town Construction Projects – Fire Station 5 (ArcGIS Story Map, Nov. 9, 2026)
  4. Flower Mound Fire Department Plans for 3 New Stations, More Staff – Community Impact
  5. Flower Mound Fire Station No. 5
  6. Flower Mound to spend $1.08M on Fire Station No. 6 design
  7. Fire Station No.5
  8. Flower Mound plans new fire station in response to population growth
  9. Highland Village News - Flower Mound breaks ground on innovative new fire station - Highland Village BubbleLife - The Online Home of Highland Village, Texas - Highland Village, Texas
  10. Flower Mound Fire Station 5, Denton: Location, Map, About & More
  11. Flower Mound Fire Department Station 5 Map - Fire station - Denton, Texas, USA
  12. Flower Mound Fire Department Station 5 in Flower Mound, TX
ShareXFacebookEmail
← back to the front page